GSE were delighted to be appointed by Costain for this project. The works firstly involved the construction of foundation to the newly located Hotel Bridge and foundations to allow the construction of the new travelator access to the North Terminal Building.


GSE also completed major highway alternation to the roads approaching the North Terminal for both dedicated airport buses and the general public vehicles.


Pavement reconstruction works to the main concourse area were carried out with phased handovers as required by the programme.


These works were carried out whilst maintaining vehicular and pedestrian access to all areas of the North Terminal for the duration of the project.