Works consisted of:
- Site clearance
- Reduce level excavation
- Mass pouring of concrete pad foundations
- Forming and pouring of 1394 m2 of reinforced structural concrete slab involving formwork and steel fixing of reinforced steel
- Construction of a lift pit involving formwork and steel fixing reinforced steel
- Constructing concrete upstands on slab
- Installation of utility service route, water, gas, electricity, electricity and data across the site penetrating the slab in areas where required
- Foul and surface water drainage installation including the installation of 100m3 capacity cellular attenuation tank
- External works including kerb installation and edging installation
- Access road, pavement and cycle way construction using permable and non-permable surfacing
- Construction of a 100m2 cycle shelter base encouraging environmentally friendly transportation usage
- Fire / maintenance access path with Bodpave Paving Grid system
- Installation of resin bound material to the entrance road leading up to the new building
Total of 34 weeks.